New enameling plant for Weber-Stephen

New enameling plant for Weber-Stephen

Ditmer Enameling Technology BV has assisted Weber-Stephen with the design, installation & commissioning of a large enameling plant for grills in Zabrze, Poland.

This project was realized in only 12 months, despite the COVID-19 epidemic.

Ditmer Enameling Technology BV has assisted Weber-Stephen with the design, installation & commissioning of a large enameling plant for grills in Zabrze, Poland.

The first phase of this project was realized in only 12 months, despite the COVID-19 epidemic, and involved the following enameling equipment :

  • one gas heated multistage spray washer with three parallel conveyors
  • one gas fired dryer
  • one advanced waste water treatment system
  • two fully automatic powder enamel systems with robots
  • Two jig cleaning booths
  • One gas fired furnace with heat-exchanger, fluor filter & cooling tunnel.

Later we also supported Weber with the implementation of a wet enameling department, consisting of :

  • enamel preparation
  • enamel spraying
  • enamel dryer
  • drying conveyor